Tashkent International Airport expands arrival hall to boost capacity
Tashkent International Airport has commenced a new phase of its reconstruction project, focusing on expanding the arrival hall. The ongoing development aims to transform the facility into a unified airport complex capable of accommodating 2,400 passengers per hour, according to a statement by Uzbekistan Airports.

The arrival hall’s floor space will be expanded by 2,500 square meters, increasing from the current 5,300 square meters. This enlargement will include:
- Installation of two additional baggage carousels
- Creation of a spacious area within the terminal for receiving passengers
During the construction period, passenger exits on the left side of the hall will be temporarily closed. Arriving passengers will exit directly through the central area of the hall, with a covered walkway being installed to ensure safety. The waiting area for receiving passengers will remain operational as usual.
The current phase of construction is scheduled for completion by May 2025. Following this, the final stage of the reconstruction project will begin, which involves integrating the departure and arrival halls. This integration will pave the way for the creation of a state-of-the-art, high-capacity airport complex.
Recommended
List of streets and intersections being repaired in Tashkent published
SOCIETY | 19:12 / 16.05.2024
Uzbekistan's flag flies high on Oceania's tallest volcano
SOCIETY | 17:54 / 15.05.2024
New tariffs to be introduced in Tashkent public transport
SOCIETY | 14:55 / 05.05.2023
Onix and Tracker cars withdrawn from sale
BUSINESS | 10:20 / 05.05.2023
Latest news
-
School placement guaranteed for all children, regardless of residency status – Ministry
SOCIETY | 14:25
-
Muhammadali Urinboev joins Royal Antwerp FC
SPORT | 14:23
-
Belarusian MTZ launches tractor assembly plant in Uzbekistan
SOCIETY | 13:39
-
Master’s admissions open: Language proficiency certificates required
SOCIETY | 13:26
Related News

15:55 / 19.06.2025
All charter flights from and to Tashkent will move to ‘Tashkent-East’ airport

20:12 / 18.06.2025
President Mirziyoyev inspects progress on Tashkent-East Airport, calls for faster completion of the project

15:51 / 01.05.2025
Urgench Airport to undergo modernization in partnership with South Korean company

14:22 / 30.04.2025